NEW QUESTION # 83
When looking at a program board at the end of program increment (Pl) planning, what does it mean when a feature is placed in a team's swim lane with no strings?
- A. That the team has not broken the feature into stories yet and has not identified dependencies
- B. That the team has been assigned, but the feature' uependencies have not been identified yet
- C. That it has dependencies on teams in other Agile release trains (ARTs) or Solution Trains
- D. That the feature can be completed by that team independently
Answer: D
NEW QUESTION # 84
In addition to Innovation and Planning, what else does the IP Iteration provide time for?
- A. An opportunity to integrate and perform end-to-end testing
- B. Additional planned work
- C. Building in quality and compliance
- D. An estimating guard band
Answer: D
NEW QUESTION # 85
When should a Product Owner (PO) develop preliminary Iteration Goals?
- A. Prior to iteration planning
- B. During PI Planning
- C. After PI Planning
- D. During backlog refinement
Answer: A
NEW QUESTION # 86
What best describes what stream-aligned teams do?
- A. Promote better flow of communications between leadership, trains and teams
- B. Build and deliver customer value with minimal dependencies on other teams
- C. Use process-mapping to identify and eliminate process bottlenecks
- D. Analyze value streams and transform them using lean-agile principles
Answer: B
NEW QUESTION # 87
What is an anti-pattern for a Release Train Engineer facilitating a scrum of scrums meet-ing?
- A. Review individual team performance
- B. Run the meeting in front of the program board
- C. Address the most important questions for Program Increment (PI) execution
- D. Facilitate the meeting using a focused and visible agenda and timebox
Answer: A
NEW QUESTION # 88
How does SAFe handle the 'fear of conflict' team dysfunction?
- A. Uses scrum to create a safe environment for conflict
- B. Avoids discussion of disagreements
- C. Reviews results at the end of every iteration
- D. Has teams engage in retrospectives
Answer: A
NEW QUESTION # 89
How can a Release Train Engineer support decentralized decision making?
- A. Empower knowledge workers to manage their dependencies with other teams
- B. Update team Program Increment (PI) Objectives when shipping a time critical re-lease
- C. Change the cadence of the Agile Release Train
- D. Evaluate the strategy for the Value Stream
Answer: A
NEW QUESTION # 90
The business must depend on the team for what in order to do any meaningful planning?
- A. Commitment to the plan
- B. Measurements
- C. Team capabilities
- D. A cross-functional skill set
Answer: A
NEW QUESTION # 91
What is one of the questions the Product Management team must answer in order to create a Vision?
- A. Which themes are on the Roadmap
- B. How many Features have already been released to the Customer
- C. Which problem will the Solution solve
Answer: C
NEW QUESTION # 92
Why should an RTE ensure that the SAFe principles are applied appropriately?
- A. To ensure that the SAFe House of Lean is reflected in standard operating proce-dure
- B. To make sure that no modifications are made by the adopters of SAFe
- C. To maintain a central control of key decision-making
- D. To build an understanding of why the lean-agile practices work
Answer: D
NEW QUESTION # 93
What action can result in reduced collaboration between teams during the Program Increment (PI) Planning event?
- A. Include inexperienced team members
- B. Skip the Inspect and Adapt event
- C. Start the Agile Release Train without a System Team in place
- D. Overprepare for PI Planning
Answer: D
NEW QUESTION # 94
What does an effective Scrum Master help the team with?
- A. Relentless improvement
- B. Deploying work
- C. Risk mitigation
- D. Team metrics
Answer: A
NEW QUESTION # 95
What can occur as a result of not having an Innovation and Planning Iteration?
- A. Delivery can be stifled incrementally
- B. Technical debt can grow uncontrollably
- C. Teams can have no time for fixing bugs
- D. Bottlenecks can be hard to identify and resolve
Answer: B
NEW QUESTION # 96
What practice can help to identify bottlenecks in the flow of work?
- A. Visualizing the flow of all work and track progress of individual items
- B. Measuring lead time for all work in progress
- C. Modeling overall process flow during value stream identification
- D. Comparing transaction costs, holding costs and business value realization
Answer: C
NEW QUESTION # 97
Which two actions can the Release Train Engineer take to facilitate team growth? (Choose two.)
- A. Provide a team vision
- B. Encourage skill specialization
- C. Ensure time is allocated for innovation and planning
- D. Facilitate conflict
- E. Encourage continuous learning
Answer: C,E
NEW QUESTION # 98
......