NEW QUESTION # 83
When looking at a program board at the end of program increment (Pl) planning, what does it mean when a feature is placed in a team's swim lane with no strings?

  • A. That the team has not broken the feature into stories yet and has not identified dependencies
  • B. That the team has been assigned, but the feature' uependencies have not been identified yet
  • C. That it has dependencies on teams in other Agile release trains (ARTs) or Solution Trains
  • D. That the feature can be completed by that team independently

Answer: D


NEW QUESTION # 84
In addition to Innovation and Planning, what else does the IP Iteration provide time for?

  • A. An opportunity to integrate and perform end-to-end testing
  • B. Additional planned work
  • C. Building in quality and compliance
  • D. An estimating guard band

Answer: D


NEW QUESTION # 85
When should a Product Owner (PO) develop preliminary Iteration Goals?

  • A. Prior to iteration planning
  • B. During PI Planning
  • C. After PI Planning
  • D. During backlog refinement

Answer: A


NEW QUESTION # 86
What best describes what stream-aligned teams do?

  • A. Promote better flow of communications between leadership, trains and teams
  • B. Build and deliver customer value with minimal dependencies on other teams
  • C. Use process-mapping to identify and eliminate process bottlenecks
  • D. Analyze value streams and transform them using lean-agile principles

Answer: B


NEW QUESTION # 87
What is an anti-pattern for a Release Train Engineer facilitating a scrum of scrums meet-ing?

  • A. Review individual team performance
  • B. Run the meeting in front of the program board
  • C. Address the most important questions for Program Increment (PI) execution
  • D. Facilitate the meeting using a focused and visible agenda and timebox

Answer: A


NEW QUESTION # 88
How does SAFe handle the 'fear of conflict' team dysfunction?

  • A. Uses scrum to create a safe environment for conflict
  • B. Avoids discussion of disagreements
  • C. Reviews results at the end of every iteration
  • D. Has teams engage in retrospectives

Answer: A


NEW QUESTION # 89
How can a Release Train Engineer support decentralized decision making?

  • A. Empower knowledge workers to manage their dependencies with other teams
  • B. Update team Program Increment (PI) Objectives when shipping a time critical re-lease
  • C. Change the cadence of the Agile Release Train
  • D. Evaluate the strategy for the Value Stream

Answer: A


NEW QUESTION # 90
The business must depend on the team for what in order to do any meaningful planning?

  • A. Commitment to the plan
  • B. Measurements
  • C. Team capabilities
  • D. A cross-functional skill set

Answer: A


NEW QUESTION # 91
What is one of the questions the Product Management team must answer in order to create a Vision?

  • A. Which themes are on the Roadmap
  • B. How many Features have already been released to the Customer
  • C. Which problem will the Solution solve

Answer: C


NEW QUESTION # 92
Why should an RTE ensure that the SAFe principles are applied appropriately?

  • A. To ensure that the SAFe House of Lean is reflected in standard operating proce-dure
  • B. To make sure that no modifications are made by the adopters of SAFe
  • C. To maintain a central control of key decision-making
  • D. To build an understanding of why the lean-agile practices work

Answer: D


NEW QUESTION # 93
What action can result in reduced collaboration between teams during the Program Increment (PI) Planning event?

  • A. Include inexperienced team members
  • B. Skip the Inspect and Adapt event
  • C. Start the Agile Release Train without a System Team in place
  • D. Overprepare for PI Planning

Answer: D


NEW QUESTION # 94
What does an effective Scrum Master help the team with?

  • A. Relentless improvement
  • B. Deploying work
  • C. Risk mitigation
  • D. Team metrics

Answer: A


NEW QUESTION # 95
What can occur as a result of not having an Innovation and Planning Iteration?

  • A. Delivery can be stifled incrementally
  • B. Technical debt can grow uncontrollably
  • C. Teams can have no time for fixing bugs
  • D. Bottlenecks can be hard to identify and resolve

Answer: B


NEW QUESTION # 96
What practice can help to identify bottlenecks in the flow of work?

  • A. Visualizing the flow of all work and track progress of individual items
  • B. Measuring lead time for all work in progress
  • C. Modeling overall process flow during value stream identification
  • D. Comparing transaction costs, holding costs and business value realization

Answer: C


NEW QUESTION # 97
Which two actions can the Release Train Engineer take to facilitate team growth? (Choose two.)

  • A. Provide a team vision
  • B. Encourage skill specialization
  • C. Ensure time is allocated for innovation and planning
  • D. Facilitate conflict
  • E. Encourage continuous learning

Answer: C,E


NEW QUESTION # 98
......